Tuesday, 3 December 2013

6th Tee Continued

Work has gone well on the 6th with its new irrigation installed last week.
 
 
 
This was followed by the rootzone being spread across both Tees ready for final levelling before turfing in the new year.


Work Continues on the 4th

The 4th is moving forward quickly thanks to the kind weather we have had for a change this last ten days, from the initial topsoil removal we have carried out the following :

Installed over 150 Metres of Drainage around the green included in this are the 2 new bunkers, and removing the need for the existing soakaway

 
Subsoiled and shaped Two new bunkers followed by topsoiling to a rough grade.  The Bunkers will be much more visable from further down the fairway having the back faces lifted to make the sand higher.

 
The two new bunkers have had the drainage completed and have been stoned ready for the next part of the work. 

 
The rest of the banking has been topsoiled ready for final grading before we turf in the New Year
 

 
 
The Banks have been built up considerably to improve the visual appearance of the hole.  It will also allow us to maintain the banking much more easily and safely therefore enabling us to keep a better surface.
 

Tuesday, 19 November 2013

6th Tee Taking Shape

Subsoil shaping has been completed for the new 6th Tees
Drain Installed through the middle of the Tee, linking into the new road drain
 
 
New Pathway being shaped

 
70/30 Rootzone being tipped ready for grading, approx. 100 tonne will be required to create a dry level teeing surface.
 
 
 
 



Work Begins on 4th Begins

Work has begun on the 4th Green Surround.  Topsoil has been stripped and subsoil is being moved from the new pond on the 2nd over to the 4th to create the mounding and bunkering around the green.


We have also been raising the canopy's of the willows behind the green to allow more light into the area. 

Tuesday, 12 November 2013

The 2nd Progress so far

Leylandii Removed from the side of the 2nd (Horrible Things) Not many left on the course now!
 
 
Topsoil Being Stripped ready for stock pilling to be used at a later stage

 
 
Topsoil Stock Piles to be used once final sub soil grading has been approved and when ground conditions permit.
 

Subsoil Shaping has began, all reusable turf stripped and reused around the course

 
Green Extension - Subsoil has been shaped and new drainage installed to the green extension

 
 
Greens Extension - Gravel Carpet being installed above the drainage runs.


The Winter Reconstruction work

Work begun on the 28th of October, work is being carried out to holes 2 4 5 & 6 to improve how the holes look and play as well as improving the overall safety of the banks which will in turn improve the quality of turf that we can provide.  The pond that is being built in front of the 2nd hole will not only add a great feature to the hole but will also provide us with the huge amounts of material required to carry out the projects this winter.  This Blog will provide a detailed summary of how the work progress's this winter.

How the green on the 2nd looked before the 28th October





Will you really miss these Bunkers ??




Bunkers that flooded whenever we had more then a few mm of rain, the shape of the bunkers are dated and do not enhance the hole in any way.


Wednesday, 9 October 2013

August Renovation

This year was the first year we have done a major renovation in August.  Usually we have carried it out towards the end of September however results can be varied depending on weather conditions.

You are now benefiting from the August renovation which has and will extended good green conditions threw to the 2nd week in November when we begin Winter aeration on them.

The Renovation Work in August included carrying out the Following

Double Scarifying


 
 Hollow Coring to  a 7 Inch Depth

 
 
Topdressed Greens - 80 tonne was applied in 3 days before a further 20 tonne was applied after seeding took place.  100 tonne in7 days not bad!
 


 
 
Power Brush - Our New machine enabled us to get the Sand into the 7 inch deep tine holes before they started to close. We  did not get bridging of the holes like we do when we use the drag mat.  It did cause a few complaints over the first couple of days with members thinking we had not done any topdressing as it was so efficient at its job.
 
 
Seeded Greens - Double Passed with the seeder applying Velvet Bent to the surface continuing our ongoing program of reducing the poa annua % in our putting greens.

 
 
Rolled Greens - To assist in getting the greens smoother and aiding soil seed contact.
 

 
 
Fertilised the Greens - To assist with Green Recovery and to give vital nutrients to the new seedlings.


 
 
This process took less then 1 week to complete and greens had recovered with within 14 days start to finish.