5th Green Surround shaping completed by using material from behind the practice green. Initial turfing has also started
Bunker Base being prepared on the 5th using type 1 granite hardcore. This is in preparation for the rubber layer being installed in house in March
4th Green Bunker having the same treatment ready for the rubber picture also shows the turfing completed apart from the actual face which will done once we have completed the rubber installation. We will also be using different turf on the faces as an experiment that should remain greener during the summer months.
Tuesday, 18 March 2014
Work Progress Jan/Feb 1
1st Tee had drainage Installed
2nd was almost completely Turfed
Lely Installed new water fountain in new 2nd Lake concreted to the base so hopefully this one does not disappear.
CONSTRUCTION CONTINUES THROUGH DECEMBER
New 5th Tee
Drainage installed to the old front tee and new raised Back Tee
One tired puppy in the office after a hard days watching !!!
Drainage installed to the old front tee and new raised Back Tee
5th Green surround and Bunkers Removed ready for new
4th Green Surround Taking Shape
5th Tee with Rootzone and Irrigation Installed (Giving us an extra 70m2)
One tired puppy in the office after a hard days watching !!!
Tuesday, 3 December 2013
6th Tee Continued
Work has gone well on the 6th with its new irrigation installed last week.
This was followed by the rootzone being spread across both Tees ready for final levelling before turfing in the new year.
Work Continues on the 4th
The 4th is moving forward quickly thanks to the kind weather we have had for a change this last ten days, from the initial topsoil removal we have carried out the following :
Installed over 150 Metres of Drainage around the green included in this are the 2 new bunkers, and removing the need for the existing soakaway
Installed over 150 Metres of Drainage around the green included in this are the 2 new bunkers, and removing the need for the existing soakaway
Subsoiled and shaped Two new bunkers followed by topsoiling to a rough grade. The Bunkers will be much more visable from further down the fairway having the back faces lifted to make the sand higher.
The two new bunkers have had the drainage completed and have been stoned ready for the next part of the work.
The rest of the banking has been topsoiled ready for final grading before we turf in the New Year
The Banks have been built up considerably to improve the visual appearance of the hole. It will also allow us to maintain the banking much more easily and safely therefore enabling us to keep a better surface.
Tuesday, 19 November 2013
6th Tee Taking Shape
Subsoil shaping has been completed for the new 6th Tees
Drain Installed through the middle of the Tee, linking into the new road drain
New Pathway being shaped
70/30 Rootzone being tipped ready for grading, approx. 100 tonne will be required to create a dry level teeing surface.
Work Begins on 4th Begins
Work has begun on the 4th Green Surround. Topsoil has been stripped and subsoil is being moved from the new pond on the 2nd over to the 4th to create the mounding and bunkering around the green.
We have also been raising the canopy's of the willows behind the green to allow more light into the area.
We have also been raising the canopy's of the willows behind the green to allow more light into the area.